Likewise, the Late Start field contains the latest date that a task can start without delaying the finish of the project. The early start is the earliest date that a task could possibly start. How Calculated Start slack is the duration that represents the difference between the early start and late start dates. The smaller of the start slack and finish slack amounts determines the amount of free slack available, that is, the amount of time a task can be delayed without affecting the start date of a successor task or the project finish date. LessÄescription The Start Slack field contains the duration between the Early Start and Late Start dates. Project Online Desktop Client Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016 Project Professional 2013 Project Standard 2013 Project 2010 Project Standard 2010 Project 2007 Project Standard 2007 More.